QUESTION 1
What do you need to do in SAP Solution Manager to convert an implementation project to solution? Note: 2 correct answers
A. Release all opened Transport into the production environment
B. Transfer the project content into the solution directory
C. Transfer business scenarios from the project to the Business Process Repository
D. Set the Project status to Closed
Answer: BC
QUESTION 2
What is the SAP tool set for the solution demo approach? Note: those 3 are correct
A. Proof of vision supported through SAP Application visualization by iRise
B. Proof of concept through prototyping
C. Predefined SAP Solution (Rapid Deployment Solutions)
Answer: ABC
QUESTION 3
What are the key concepts of the SAP blueprint approach? Note: 3 correct answer
A. Configuration Management
B. Value Realization
C. Business Process Management
D. Acceleration Techniques
E. Test Management
Answer: BCD
QUESTION 4
How do you access the SAP Modeling Handbook?
A. As a book published by SAP PRESS
B. As an adobe PDF on the SAP Public website
C. As part of the documentation available on the SAP Help Portal
D. As Wiki pages on the SAP Community Network (SCN)
Answer: D
QUESTION 5
What tasks in the Business Blueprint phase do you execute to define the Organizational Change Management (OCM) Communication plan? Note: 2 correct answers
A. Define Project Organization
B. Define Communication Strategy
C. Define value argumentation and key messages
D. Refine Acceptance Criteria
Answer: BC
QUESTION 6
What is the purpose of the Value Realization deliverable?
A. Value Realization focuses on the Technical optimization business processes and alignment of all aspects of an organization
B. Value Realization ensures an optimized SAP Solution operation by providing applicable content for setting up operations.
C. Value Realization establishes sustainable mechanisms to monitor and control the predefined KPIs and PPIs of the to-be process
D. Value Realization provides proactive procedures to minimize the impact of critical situations
Answer: C
QUESTION 7
Which template do you use to describe the solution for identified gaps during blueprinting?
A. Gap Analysis Findings Template
B. Functional Specification Template
C. Business Process Map template
D. Technical Specification Template
Answer: B
QUESTION 8
What are the attributes available in ASAP on deliverable level? Note: 2 correct answers
A. Accelerators
B. Work Stream Assignments
C. Milestone
D. Accountable Roles
Answer: AB
GreatExam gives the latest, authoritative and complete C_PM_71 braindumps for C_PM_71 exam, because of that, all of our candidates pass C_PM_71 certification without any problem. The biggest feature is the regular update of C_PM_71 PDF and VCE, which keeps our candidates’ knowledge up to date and ensures their C_PM_71 exam success.
2016 SAP C_PM_71 exam dumps (All 85 Q&As) from GreatExam:
http://www.greatexam.com/c-pm-71-exam-questions.html [100% Exam Pass Guaranteed!!!]
Comments are closed.